Decision desk / 03
Award decision desk
Does the intended mechanical award include controls wiring between the roof units and the building controller?
The source record
Mechanical scope sheet / Item 18
The scope sheet assigns controls wiring to the mechanical trade.
Mechanical proposal / Exclusion 7
The proposal excludes controls power and interconnecting wiring.
The review question
Resolve the controls wiring boundary before award.
The review would flag the conflict, draft the clarification, and leave final approval with the team.
Project team action
Record the decision at the gate.
- Owner
- Project manager
- Timing
- Before subcontract execution
- Action
- The project manager aligns the proposal and scope sheet, then carries the accepted boundary into the subcontract exhibit.
- Record
- Award recommendation and subcontract exhibit