Document basis
Northline Operations Center
Decision: electrical trade scope confirmation before quote leveling.
Source references
Two drawings describe panel DP-1. The marked values disagree.
Source A / Drawing E-601
Electrical equipment schedule, row DP-1
Distribution panel DP-1, 800A main.
Source B / Drawing E-501
Single-line diagram, panel DP-1
DP-1 shown with a 600A main.
Carried in the bid scope. Electrical trade scope § 2.4: Furnish and install distribution panel DP-1 with a 600A main.
Review item 01
DP-1 has an 800A main on the E-601 schedule and a 600A main on the E-501 single-line.
Both drawings describe the same panel, so the bid has no single basis for DP-1 until the design team confirms the required rating. Electrical trade scope § 2.4 carries the 600A value.
Draft RFI
Distribution panel DP-1: required main rating
- To
- Design team (electrical)
- References
- Drawing E-601, electrical equipment schedule, row DP-1. Drawing E-501, single-line diagram, panel DP-1.
- Background
- The E-601 equipment schedule lists distribution panel DP-1 with an 800A main. The E-501 single-line diagram shows DP-1 with a 600A main.
- Question
- Please confirm the required main rating for DP-1 and revise the drawing that does not match.
Recommended action
Issue the RFI, confirm which main rating electrical bidders priced, and revise § 2.4 to the confirmed rating before quote leveling.
- Owner
- Project manager / electrical estimator
- Timing
- Before quote leveling
- Record
- Log the response in the clarification log and carry the confirmed rating in the accepted trade scope.