Document basis
Northline Operations Center
Decision: electrical trade scope confirmation before bid leveling.
Source references
Drawing E-601
Equipment schedule identifies distribution panel DP-1 with an 800A main.
Electrical trade scope § 2.4
Includes distribution equipment shown on the one-line diagram and schedules.
Review item 01
Confirm the controlling equipment rating before the scope is carried.
The accepted sources refer to the same equipment but do not establish a consistent basis for the bid. The project team should confirm which requirement controls and record that decision in the trade scope.
Draft RFI
Distribution panel DP-1 rating
Please confirm the required rating for distribution panel DP-1 and identify the controlling drawing, schedule, or specification. Confirm whether the electrical trade scope should be revised to carry that requirement.
Recommended action
Resolve and document before quote leveling.
- Owner
- Project manager / electrical estimator
- Timing
- Before final scope alignment
- Record
- Update the clarification log and accepted trade scope after the response is received.