Skip to content
Sample Report

Westside Medical Office Building

This scope gap analysis of the Westside Medical Office Building identified 7 findings across the construction drawings, AIA contract, and MEP scope sheets.

Analyzed

2026-02-25

Completion

8m 30s

Risk Score

74/100

Findings

7

Exposure (Low)

$185,000

Exposure (High)

$412,000

Executive Summary

This scope gap analysis of the Westside Medical Office Building identified 7 findings across the construction drawings, AIA contract, and MEP scope sheets. The most critical finding is unassigned fire-rated corridor work ($85K–$180K exposure) where the drawings show 2-hour assemblies but no trade scope explicitly includes this work.

Detailed Findings

By severity: 2 Critical 2 High 2 Medium 1 Low
SG-001 SEVERITY 4 — CRITICAL Missed Scope

Fire-Rated Corridor Assemblies Not Assigned to Any Trade

Drawing sheets A-201 and A-202 call for 2-hour fire-rated corridor assemblies throughout the Level 1 patient corridor.

Why It Matters

Fire-rated assemblies are required by the AHJ for Certificate of Occupancy. Unassigned work will emerge as a change order, potentially delaying CO by weeks.

Drawing Reference

A-201 keynote 14, A-202 wall type WA-7

Contract Reference

Division 09 scope excludes fire-rated assemblies per exhibit B

Framing Drywall Fire Protection

Financial Exposure

$85,000 – $180,000

RFI #001

Please confirm which trade is responsible for the fire-rated corridor assemblies, and provide a complete scope breakdown for this work including blocking, shaft liner, and fire caulking.

SG-002 SEVERITY 3 — HIGH Trade Overlap

Rooftop Equipment Curbs — Roofing vs. Mechanical Overlap

The mechanical scope includes rooftop RTUs and references "contractor-furnished curbs." The roofing scope also includes "all rooftop curb flashings."

Why It Matters

Overlapping scope creates duplicate change orders if both trades bill for the same work during construction.

Drawing Reference

M-501 equipment schedule, roof plan R-100

Contract Reference

Division 15 sec. 2.3 and Division 07 sec. 4.1

Mechanical Roofing

Financial Exposure

$18,000 – $35,000

RFI #002

Please clarify: (1) who furnishes the curbs, (2) who installs the curbs, and (3) who is responsible for curb flashing and waterproofing.

SG-003 SEVERITY 3 — HIGH Missed Scope

MEP Coordination Gap in Procedure Room Corridor

The electrical scope references "coordinate with mechanical for ceiling heights in procedure corridor." The mechanical scope has no corresponding coordination note. The reflected ceiling plan (A-601) shows a 9'-0" finished ceiling, but the ductwork on M-301 would result in 8'-2" clearance.

Why It Matters

Ceiling height conflict will require field modifications to ductwork or structure, triggering change orders from both mechanical and electrical trades.

Drawing Reference

A-601 RCP, M-301 ductwork plan

Contract Reference

Electrical scope exhibit C note 7

Mechanical Electrical Ceiling

Financial Exposure

$22,000 – $48,000

RFI #003

Please provide confirmation of design intent and coordination responsibility for the procedure room corridor ceiling height conflict between the reflected ceiling plan (A-601, 9'-0") and the mechanical ductwork plan (M-301, resulting in 8'-2" clearance).

SG-004 SEVERITY 2 — MEDIUM Missed Scope

Elevator Pit Waterproofing Not in Any Trade Scope

The structural drawings (S-101) show an elevator pit with waterproofing notes. The elevator contractor scope excludes below-grade waterproofing.

Why It Matters

Elevator pit waterproofing is required before elevator installation. Missing assignment causes schedule delays and cost disputes.

Drawing Reference

S-101 elevator pit detail, sheet A-501

Contract Reference

Elevator scope exclusion list item 12

Concrete Waterproofing Elevator

Financial Exposure

$8,000 – $18,000

RFI #004

Please clarify which trade is responsible for elevator pit waterproofing as shown on S-101 detail 4.

SG-005 SEVERITY 2 — MEDIUM Contractual Issue

Kitchen Hood Exhaust — Mechanical vs. Food Service Equipment Gap

The kitchen equipment contractor scope ends at the hood connection point. The mechanical scope references "existing duct" for kitchen exhaust, but this is a new building.

Why It Matters

Kitchen hood exhaust is a health code requirement. Unassigned ductwork will generate a late-project change order.

Drawing Reference

M-201 kitchen exhaust routing, K-101 equipment plan

Contract Reference

Food service scope section 3 connection requirements

Mechanical Food Service Equipment

Financial Exposure

$12,000 – $28,000

RFI #005

Please clarify who is responsible for the kitchen exhaust ductwork from hood to exterior discharge point.

SG-006 SEVERITY 1 — LOW Contractual Issue

Medical Gas Rough-In — Plumbing Scope Ambiguity

The plumbing scope includes "medical gas rough-in per drawings." The medical gas contractor scope also includes "all piping."

Why It Matters

Duplicate scopes result in double billing. Requires clarification before both trades are under contract.

Drawing Reference

P-201 medical gas plan

Contract Reference

Plumbing scope 2.4, Medical Gas scope 1.2

Plumbing Medical Gas

Financial Exposure

$15,000 – $55,000

RFI #006

Please define the scope boundary between these two trades, specifying where plumbing responsibility ends and medical gas contractor responsibility begins.

SG-007 SEVERITY 1 — LOW Missed Scope

Site Lighting — Civil vs. Electrical Scope Boundary

The civil drawings show 12 site light pole foundations. The civil scope includes "earthwork and grading only." The electrical scope includes "site lighting as shown on E-series drawings" but E-series drawings don't include pole foundations.

Why It Matters

Site light pole foundations are required for exterior lighting installation. Unassigned scope delays site lighting completion.

Drawing Reference

C-501 site plan, E-601 site lighting

Contract Reference

Civil scope section 2 earthwork exclusions

Civil Electrical Concrete

Financial Exposure

$25,000 – $48,000

RFI #007

Please assign pole foundation responsibility and confirm whether a concrete contractor is needed for the 12 site light pole foundations shown on C-501.

Recommended Actions

1

Issue RFI to clarify responsibility for fire-rated corridor assemblies

GC Preconstruction · Before bid day

2

Reconcile MEP scope sheets with drawing set A-401 through A-408

MEP Coordinator · Within 5 business days

3

Confirm rooftop equipment curb responsibility between roofing and mechanical

GC PM · Before subcontract execution

Ready to analyze your project?

Upload your documents and get a scope gap report like this one in minutes.